Proton Calorimetry/Experimental Runs/2022/Sep1
Detector Equipment
- C-section stack holder containing 25 clear scintillator sheets around 2.86 mm thick with 24 sheets of mylar foil. Add 25th sheet of Mylar?
- C-section stack holder containing 23 white painted scintillator sheets around 2.86 mm thick.
- Zarges case.
- Clatterbridge stack A and B (to be assembled during beam test)
- DDC232 rev. B x2 & Nexys Video.
- Single Scintillator Block & camera.
Experiment Plan
Estimated first beam: 16.00.
- Set up mains cabling and networking in treatment and control rooms.
- Install Peli case and Giraffe on treatment couch:
- Set up 2 x 2.86mm stacks for shoot through measurement of range pullback at ~245MeV (no DAQ needed).
- Align Peli case and Giraffe using in-room lasers.
- Measure range pullback of combined stack, each individual stack and empty case.
- Set up Peli case for range pullback measurement of single block:
- Remove long rail from Peli case and install single scintillator block.
- Simultaneously dismantle 2 x 2.86mm stacks and assemble Clatterbridge stacks with rev.B DDC board.
- Check alignment of Peli case and Giraffe.
- Measure range pullback of single block.
- Set up Peli case for range pullback measurement of 32 x 3mm stack:
- Remove single scintillator block.
- Install 32 x 3mm stack with rotated rail; reinstall long rail.
- Simultaneously install single scintillator block in Zarges case with camera.
- Check alignment of Peli case and Giraffe.
- Measure range pullback of 32 x 3mm stack.
- Set up Peli case for range pullback measurement of Clatterbridge stacks:
- Remove 32 x 3mm stack; install Clatterbridge stacks on long rail and clamp in place.
- Check alignment of Peli case and Giraffe.
- Measure range pullback of Clatterbridge stacks together and individually.
- Set up Zarges case for single block quenching measurements:
- Remove Peli case and Giraffe from treatment couch.
- Install Zarges case on treatment couch and align with room lasers.
- Connect DAQ and check camera functionality.
- Simultaneously set up Peli case with Clatterbridge stacks and FPGAs ready for shoot throughs.
- Measure light output from shoot through and set exposure time.
- Record photos of single block light output for energies from 70 MeV to ~150MeV (maximum energy with beam still in block).
- Set up Peli case for Clatterbridge DAQ measurements:
- Remove Zarges case from treatment couch; install Peli case with FPGA, cabling and Clatterbridge stacks.
- Check alignment of Peli case and DAQ hardware.
- Record DDC calibration data for shoot through and background.
- Set up Peli case for 32 x 3mm stack measurements:
- Remove Clatterbridge stacks and store safely.
- Install 32 x 3mm stack in Peli case with rev.C/D DDC board.
- Check alignment of Peli case and DAQ hardware.
- Measure background and shoot through of 32 x 3mm stack.
- Measure proton energies in range 70–110 MeV.
- Dismantle equipment, pack up and fuck off.
- WET measurement of stack of clear sheets with mylar foil.
- Addition of stack of white painted sheets for WET measurement of both stacks.
- Removal of stack of clear sheets for WET measurement of stack of white painted sheets.
- WET measurement of Zarges case with mylar windows without any stacks of scintillator.
- Quenching measurements?
- Assemble Clatterbridge stacks during these measurements
- Calibration shoot-through measurements for Clatterbridge stacks.
- Possible WET measurement of Clatterbridge A stack?