Proton Calorimetry/Meetings/2017/07/18: Difference between revisions
SimonJolly (talk | contribs) No edit summary |
SimonJolly (talk | contribs) No edit summary |
||
Line 32: | Line 32: | ||
'''Dates Away''': | '''Dates Away''': | ||
; SJ : 28th July–11th August (holiday), 28th August–1st September (AWAKE installations), 4th–14th September (China). | ; SJ : 28th July–11th August (holiday but contactable), 28th August–1st September (AWAKE installations), 4th–14th September (China). | ||
; ABF : 29th July–5th August, 10th–21st August. | ; ABF : 29th July–5th August (holiday, maybe internet), 10th–21st August (no internet). | ||
; RS : 7th–11th August (Modane), 18th August–2nd September (holiday). | ; RS : 7th–11th August (Modane), 18th August–2nd September (holiday). |
Revision as of 13:55, 18 July 2017
Minutes for UCL Proton Calorimetry Meeting, 5th July 2017 (D107, Physics & Astronomy, UCL)
Present
Simon Jolly, Anastasia Basharina-Freshville, Ruben Saakyan
RS:
- PMT bases are on their way from Hamamatsu!
- Start with testing dynode 4 and 5.
- Measure peak and average anode current with LEDs.
- Check low rate performance first, then increase rate to check whether distortion occurs above 1MHz.
- Gated PMT will require a bit more thought...
- Scintillator sheets also shipped from Nuvia:
- Samples of 100x100x10mm, standard and pTP enhanced composition, 0.3mm foil to be cut as needed.
- Also 3mm pressed material included.
- WaveCatcher documentation for hardware and software available from Orsay:
- 2–64 channel versions available.
- Seems similar to Caen but with access to firmware.
ABF:
- Applied bias voltage to photodiode preamp: signal increases, so does noise...
- Will check photodiode with 1–100 ms integration windows.
- Will also check maximum integration window for Caen DT5740D QDC 16-channel digitiser.
SJ:
- SMA components mostly here:
- High quality Huber and Suhner components ordered for proton calorimetry; LOTS of less expensive (but still decent) spares available within group.
- SMA-BNC and SMA-MCX adapters all arrived.
- Waiting on 2:1 Mini-Circuits splitter.
- Various lengths of Huber and Suhner SMA cable borrowed from John Mitchell (UCL Electrical Engineering).
- Will email Ferruccio Renzoni and Peter Barker regarding coupling of photodiodes to electronics.
Dates Away:
- SJ
- 28th July–11th August (holiday but contactable), 28th August–1st September (AWAKE installations), 4th–14th September (China).
- ABF
- 29th July–5th August (holiday, maybe internet), 10th–21st August (no internet).
- RS
- 7th–11th August (Modane), 18th August–2nd September (holiday).